San Francisco / Inner Richmond / 4200 Geary Bl

4200 Geary Bl

98-unit 7-story residential project 100% affordable housing

Complete98 UnitsAB 2011 MinisterialDBI Valuation $44.8M
Entitlement
Plan Check
Aug 2021
Awaiting Issuance
Aug 2021
Post-Issuance Addenda
Construction
May 2025
Complete
May 2025
Permit Filed
Sep 2020
Time in Active Review
11 months
excludes 17 months dormant
Completed
May 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

August 2021

Permit issued on August 20, 2021. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeAugust 20, 2021
Key Milestones
Sep 2020
Permit Filed
New construction permit filed with DBI
Sep 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2021
Permit Issued
Construction can begin
Sep 2021
Dormant Period
No plan-check activity for ~17 months — applicant-side pause, not city queue time.
May 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Aug 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 11 mo · Applicant: 1 mo · Dormant: 17 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Hu Qi (Anne).
In Review
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Dito Matthew.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Woo Jason.
In Review
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date. Reviewer: Stacy Sara.
In Review
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 1 cycle(s) to date. Reviewer: Ospital Joseph.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: May 2025
Construction startedJun 2023
Total inspections157
98 of 98 units certified for occupancy (Amended TCO, May 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-08-29
106FINAL INSPECT/APPRVDPASSED
2025-06-20
142PRE-FINAL
2025-06-04
134OK TO COVERPASSED
2025-05-09
145TCO ISSUEDPASSED
2025-05-09
134OK TO COVER
2025-05-08
134OK TO COVER
2025-05-07
134OK TO COVER
2025-05-02
134OK TO COVERPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.