San Francisco / South of Market / 600 07Th St

600 07Th St

221-unit 8-story residential project to erect a 8-story, type 1b, mixed use bldg with 221 residential unit, no basement

Complete221 UnitsAB 2011 MinisterialDBI Valuation $82.1M
Entitlement
Plan Check
Nov 2021
Awaiting Issuance
Nov 2021
Post-Issuance Addenda
Construction
Jan 2025
Complete
Jan 2025
Permit Filed
Oct 2020
Time in Active Review
13 months
Completed
Jan 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

November 2021

Permit issued on November 22, 2021. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeNovember 22, 2021
Key Milestones
Oct 2020
Permit Filed
New construction permit filed with DBI
Oct 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2021
Permit Issued
Construction can begin
Dec 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Sep 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 13 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 4 cycle(s) to date. Reviewer: Liang Xinyu.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Ralls Matthew.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
In Review
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Dec 2024
Construction startedAug 2022
Total inspections115
115 of 221 units certified for occupancy (Amended TCO, Jan 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-09-04
106FINAL INSPECT/APPRVDPASSED
2025-05-15
142PRE-FINALPASSED
2025-02-13
125ROUGH FRAME, PARTIALPASSED
2025-01-21
145TCO ISSUED
2024-12-10
145TCO ISSUEDPASSED
2024-12-06
142PRE-FINAL
2024-12-05
142PRE-FINAL
2024-11-27
142PRE-FINAL
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.