Estimated Timeline
0 of 8 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 4 cycle(s) to date. Reviewer: Liang Xinyu.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Ralls Matthew.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Andrawes Kamal.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Oct 2020
Permit Filed
New construction permit filed with DBI
Oct 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2021
Permit Issued
Construction can begin
Sep 2025
Construction Complete
Certificate of occupancy issued