Estimated Timeline
4 of 6 stations approved66% complete
Key Milestones
Oct 2020
Permit Filed
New construction permit filed with DBI
Nov 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2022
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jun 2023
Dormant Period
No plan-check activity for ~35 months — applicant-side pause, not city queue time.
Jun 2026
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 20 mo · Applicant: 3 mo · Dormant: 46 mo
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on May 28, 2026. 2 round(s) of review. Reviewer: Chung Diana.
Fire (SFFD)
SF Fire Department
Currently in review. 4 cycle(s) to date. Reviewer: Ziegler Erik.
Planning (CP-ZOC)
SF Planning Department
Approved June 01, 2026. Reviewer: Tam Tina.
Building Code (BLDG)
Dept. of Building Inspection
Approved June 18, 2026. Reviewer: Liu Chu.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved May 27, 2026. Reviewer: Dennis Rassendyll.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved April 21, 2022. Reviewer: Blackshear John.
Bottleneck Watch: Fire
Fire is the longest-running active review station on this project.