Estimated Timeline
0 of 5 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Ajello Hoagland Linda.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Yin Diane.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Long Ian.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Nov 2020
Permit Filed
New construction permit filed with DBI
Nov 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2022
Permit Issued
Construction can begin
Mar 2026
Construction Complete
Certificate of occupancy issued