San Francisco / South of Market / 580 Minna St

580 Minna St

20-unit 7-story residential project erect a seven story type 1-a construction 20 units one basement residential building

Permit Filed — In Plan Check20 UnitsAB 2011 Ministerial$5.5M Est. Cost
Permit Filed
Dec 2020
Active Review Since
Dec 2020
Review Stations
0 of 8
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

November 2026 — February 2028

Timeline driven by 1 station with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 8 unapproved stations
0 of 8 stations approved0% complete
Plan Check Status
Mental Health (HEALTH-MH)
Dept. of Public Health
Comments issued on November 18, 2022. 1 round(s) of review. Reviewer: Chen Bill.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Samonsky Ella.
In Review
Neighborhood Planning (CP-NP)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Samonsky Ella.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Not Yet Routed
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Not Yet Routed
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Not Yet Routed
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Not Yet Routed

Bottleneck Watch: Fire

Fire has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.

Key Milestones
Dec 2020
Permit Filed
New construction permit filed with DBI
Dec 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – Feb 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.