San Francisco / Mission / 733 Treat Av

733 Treat Av

7-unit 5-story residential project erect a five story type iii-a construction no basement 7 units residential building (5th story not a penthouse per bldg elevator housing, four stories of occ...

Permit Issued7 UnitsAB 2011 MinisterialDBI Valuation $3.0M
Entitlement
Plan Check
May 2023
Awaiting Issuance
May 2023
Post-Issuance Addenda
Construction
Complete
Construction: Foundation / Pour (25%). Last inspection: Jun 2026.
Permit Filed
Dec 2020
Time in Active Review
18 months
excludes 10 months dormant
Permit Issued
May 2023
plan check complete
Project Status
Permit Issued
Estimated Timeline

Permit Issued

May 2023

Permit issued on May 03, 2023. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeMay 03, 2023
Key Milestones
Dec 2020
Permit Filed
New construction permit filed with DBI
Dec 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2021
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
May 2023
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 18 mo · Applicant: 0 mo · Dormant: 10 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 4 cycle(s) to date. Reviewer: Samonsky Ella.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Pang David.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Rhab Boughn.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 2 cycle(s) to date. Reviewer: Hoffman Daniel.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Imson Grace.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Foundation / Pour
25% completeLatest inspection: Jun 2026
Construction startedJun 2026
Total inspections8
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-20
125ROUGH FRAME, PARTIAL
2026-07-15
123OK TO POUR
2026-07-14
123OK TO POUR
2026-07-10
123OK TO POUR
2026-07-06
123OK TO POUR
2026-06-29
123OK TO POUR
2026-06-26
123OK TO POURPASSED
2026-06-24
101START WORKPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.