Estimated Timeline
Permit issued — plan check completeMay 03, 2023
Key Milestones
Dec 2020
Permit Filed
New construction permit filed with DBI
Dec 2020
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2021
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
May 2023
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 18 mo · Applicant: 0 mo · Dormant: 10 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 4 cycle(s) to date. Reviewer: Samonsky Ella.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Pang David.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Rhab Boughn.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 2 cycle(s) to date. Reviewer: Hoffman Daniel.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Imson Grace.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Foundation / Pour
25% completeLatest inspection: Jun 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-20
125ROUGH FRAME, PARTIAL
2026-07-15
123OK TO POUR
2026-07-14
123OK TO POUR
2026-07-10
123OK TO POUR
2026-07-06
123OK TO POUR
2026-06-29
123OK TO POUR
2026-06-26
123OK TO POURPASSED
2026-06-24
101START WORKPASSED