Estimated Timeline
Permit issued — plan check completeOctober 02, 2023
Key Milestones
Jan 2021
Permit Filed
New construction permit filed with DBI
Jan 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2021
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Dec 2021
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Sep 2022
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Sep 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Oct 2023
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 11 mo · Applicant: 1 mo · Dormant: 20 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Mcelroy Carey.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Mann Kerry.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Chung Diana.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 3 cycle(s) to date. Reviewer: Hoffman Daniel.
Planning (CP-ZOC)
SF Planning Department
Approved September 19, 2023. Reviewer: Agnihotri Kalyani.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved September 20, 2023. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.