San Francisco / Tenderloin / 240 Van Ness Av

240 Van Ness Av

112-unit 8-story residential project to erect a type 1-b, 8-story, 112 units, mixed-use building with ground flr office/commercial space and no basement level

Complete112 UnitsAB 2011 MinisterialDBI Valuation $40.1M
Entitlement
Plan Check
Jan 2022
Awaiting Issuance
Jan 2022
Post-Issuance Addenda
Construction
Apr 2025
Complete
Apr 2025
Permit Filed
Jan 2021
Time in Active Review
13 months
Completed
Apr 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

January 2022

Permit issued on January 24, 2022. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJanuary 24, 2022
Key Milestones
Jan 2021
Permit Filed
New construction permit filed with DBI
Jan 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Jan 2022
Permit Issued
Construction can begin
Apr 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Oct 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 13 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Asbagh Claudine.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Liang Karen.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Tom Bill.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Casey Ryan.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Jan 2025
Construction startedMay 2023
Total inspections116
112 of 112 units certified for occupancy (Initial TCO, Apr 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-10-31
106FINAL INSPECT/APPRVD
2025-10-31
106FINAL INSPECT/APPRVDPASSED
2025-03-11
125ROUGH FRAME, PARTIAL
2025-03-10
125ROUGH FRAME, PARTIAL
2025-02-13
142PRE-FINAL
2025-02-06
134OK TO COVERPASSED
2025-01-31
142PRE-FINAL
2025-01-30
142PRE-FINALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.