Estimated Timeline
0 of 10 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Liang Xinyu.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Chan Janey.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Estrella Jerry.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Imson Grace.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Hazmat (HEALTH-HM)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Chan Thomas.
Mental Health (HEALTH-MH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 2 cycle(s) to date. Reviewer: Bryan Ong.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Feb 2021
Permit Filed
New construction permit filed with DBI
Feb 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2022
Permit Issued
Construction can begin