Estimated Timeline
Permit issued — plan check completeNovember 22, 2022
Key Milestones
Feb 2021
Permit Filed
New construction permit filed with DBI
Feb 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2021
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Nov 2021
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Nov 2022
Permit Issued
Construction can begin
Apr 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 0 mo · Dormant: 14 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Liang Xinyu.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Chan Janey.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Estrella Jerry.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Imson Grace.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Hazardous Materials (HEALTH-HM)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Chan Thomas.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 2 cycle(s) to date. Reviewer: Bryan Ong.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Certified for Occupancy
100% completeLatest inspection: May 2025
501 of 501 units certified for occupancy (Initial TCO, Apr 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-07-09
800INSP QUALITY CONTROL OFFICE
2025-05-13
145TCO ISSUEDPASSED
2025-05-12
126ROUGH FRAMEPASSED
2025-05-12
126ROUGH FRAME
2025-04-23
145TCO ISSUEDPASSED
2025-04-23
142PRE-FINALPASSED
2025-04-18
111SITE VERIFICATION
2025-04-17
126ROUGH FRAME