Estimated Timeline
1 of 6 stations approved16% complete
Key Milestones
Feb 2021
Permit Filed
New construction permit filed with DBI
Feb 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2021
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
Jul 2022
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Jul 2023
Currently Dormant
No plan-check activity for 1144 days so far — applicant-side pause, not city queue time.
Dec 2026 – Oct 2029
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 7 mo · Applicant: 0 mo · Dormant: 59 mo
Planning (CP-ZOC)
SF Planning Department
Comments issued on June 25, 2021. 1 round(s) of review. Reviewer: Alexander Christy.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Building Code (BLDG)
Dept. of Building Inspection
Approved July 10, 2023. Reviewer: Zee Howard.
Bottleneck Watch: Sidewalk & Street
Sidewalk & Street has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.