Estimated Timeline
Permit issued — plan check completeAugust 13, 2021
Key Milestones
Mar 2021
Permit Filed
New construction permit filed with DBI
Mar 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2021
Permit Issued
Construction can begin
Oct 2024
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jan 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 5 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Liu Stephen.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Andrawes Kamal.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Tom Bill.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: Oct 2024
148 of 148 units certified for occupancy (Initial TCO, Oct 2024).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-01-08
142PRE-FINALPASSED
2024-12-12
111SITE VERIFICATION
2024-10-23
145TCO ISSUEDPASSED
2024-10-21
134OK TO COVER
2024-10-15
134OK TO COVER
2024-10-10
134OK TO COVER
2024-10-07
134OK TO COVER
2024-10-03
145TCO ISSUED