San Francisco / Haight Ashbury / 730 Stanyan St

730 Stanyan St

160-unit 8-story residential project new 8-story building containing 175,426 square feet of residential uses above 12,556 square feet of ground floor commercial uses on vacant lot

Construction Complete160 UnitsAB 2011 Ministerial$60.0M Est. Cost
Permit Filed
Mar 2021
Active Review Since
Mar 2021
Review Stations
0 of 9
stations approved
Project Status
Complete
Estimated Timeline

Permit Issued

December 2022

Permit issued on December 28, 2022. Project moved into construction phase.

Actual permit issuance date from DBI records
0 of 9 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: May Christopher.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Yin Diane.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 3 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Woo Jason.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Fong Jeffrey.
In Review
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
In Review
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date. Reviewer: Hoffman Daniel.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Cheng Rachel.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Mar 2021
Permit Filed
New construction permit filed with DBI
Mar 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Permit Issued
Construction can begin
Nov 2025
Construction Complete
Certificate of occupancy issued
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.