Estimated Timeline
Permit issued — plan check completeApril 26, 2021
Key Milestones
Apr 2021
Permit Filed
New construction permit filed with DBI
Apr 2021
Permit Issued
Construction can begin
May 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Nov 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Woo Jason.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Fong Jeffrey.
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 2 cycle(s) to date. Reviewer: Ospital Joseph.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Construction
Construction Complete
100% completeLatest inspection: May 2025
71 of 73 units certified for occupancy (Amended TCO, Mar 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-11-24
106FINAL INSPECT/APPRVDPASSED
2025-11-21
106FINAL INSPECT/APPRVDPASSED
2025-05-09
145TCO ISSUEDPASSED
2025-04-28
145TCO ISSUEDPASSED
2025-04-16
142PRE-FINALPASSED
2025-03-13
145TCO ISSUEDPASSED
2025-03-12
142PRE-FINALPASSED
2025-03-12
142PRE-FINAL