Estimated Timeline
Permit issued — plan check completeNovember 02, 2022
Key Milestones
May 2021
Permit Filed
New construction permit filed with DBI
May 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2022
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 18 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Pantoja Gabriela.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Chan Philip.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Matsubayashi Sean.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Imson Grace.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.