San Francisco / Mission / 2955 Mission St

2955 Mission St

18-unit 5-story residential project construct 6-story w/ 1 basement, 18-unit, mixed-use building

Permit Filed — In Plan Check18 UnitsStandard Entitlement$5.0M Est. Cost
Permit Filed
May 2021
Active Review Since
Oct 2022
Review Stations
0 of 6
stations approved
Project Status
Filed
Estimated Timeline

Permit Issuance Estimate

November 2026 — May 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 6 unapproved stations
0 of 6 stations approved0% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Comments issued on April 02, 2026. 2 round(s) of review. Reviewer: Giacomucci Monica.
Comments Issued
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on July 27, 2023. 2 round(s) of review. Reviewer: Wong Irene.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on March 04, 2023. 1 round(s) of review. Reviewer: Estrella Jerry.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on July 26, 2023. 1 round(s) of review. Reviewer: Mautner Allegra.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Kevin Li.
In Review

Bottleneck Watch: Planning

Planning currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Key Milestones
May 2021
Permit Filed
New construction permit filed with DBI
Oct 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.