San Francisco / Mission / 2955 Mission St

2955 Mission St

18-unit 5-story residential project construct 6-story w/ 1 basement, 18-unit, mixed-use building

In Plan Check18 UnitsStandard EntitlementDBI Valuation $5.0M
Entitlement
Nov 2022
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: 14 months in active review. City desk: 9 mo · Applicant: 5 mo
Permit Filed
May 2021
Time in Active Review
14 months
excludes 32 months dormant
Review Stations
0 of 6
stations approved
Project Status
In Plan Check
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 6 unapproved stations
0 of 6 stations approved0% complete
Key Milestones
May 2021
Permit Filed
New construction permit filed with DBI
Oct 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2023
Dormant Period
No plan-check activity for ~32 months — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 9 mo · Applicant: 5 mo · Dormant: 32 mo
Planning (CP-ZOC)
SF Planning Department
Comments issued on April 02, 2026. 2 round(s) of review. Reviewer: Giacomucci Monica.
Comments Issued
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on July 27, 2023. 2 round(s) of review. Reviewer: Wong Irene.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on March 04, 2023. 1 round(s) of review. Reviewer: Estrella Jerry.
Comments Issued
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on July 26, 2023. 1 round(s) of review. Reviewer: Mautner Allegra.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Garcia Jobel.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Kevin Li.
In Review

Bottleneck Watch: Planning

Planning currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.