San Francisco / Visitacion Valley / 1501 Sunnydale Av

1501 Sunnydale Av

90-unit 5-story residential project sunnydale block 3b (lot 4) - mayor ed 13-01 & 17-02: priority 100% housing project

Complete90 UnitsAB 2011 MinisterialDBI Valuation $62.0M
Entitlement
Plan Check
May 2022
Awaiting Issuance
May 2022
Post-Issuance Addenda
Construction
Feb 2025
Complete
Feb 2025
Permit Filed
Jun 2021
Time in Active Review
11 months
Completed
Feb 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

May 2022

Permit issued on May 12, 2022. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeMay 12, 2022
Key Milestones
Jun 2021
Permit Filed
New construction permit filed with DBI
Jun 2021
Electronic Plan Review Activated
Plans distributed to all review stations
May 2022
Permit Issued
Construction can begin
Feb 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Apr 2025
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 11 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Durandet Kimberly.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Hu Qi (Anne).
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Der Kristine.
In Review
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 1 cycle(s) to date. Reviewer: Ospital Joseph.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Long Ian.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Construction Complete
100% completeLatest inspection: Feb 2025
Construction startedJun 2023
Total inspections114
90 of 90 units certified for occupancy (Initial TCO, Feb 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2025-04-28
106FINAL INSPECT/APPRVDPASSED
2025-04-16
142PRE-FINAL
2025-03-18
142PRE-FINAL
2025-02-20
145TCO ISSUEDPASSED
2025-02-18
142PRE-FINALFAILED
2025-02-14
142PRE-FINAL
2025-02-13
142PRE-FINAL
2025-02-12
142PRE-FINAL
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.