Estimated Timeline
1 of 8 stations approved12% complete
Key Milestones
Jun 2021
Permit Filed
New construction permit filed with DBI
Jul 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jun 2023
Dormant Period
No plan-check activity for ~34 months — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 27 mo · Applicant: 0 mo · Dormant: 34 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Mcelroy Carey.
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Ortega Reynaldo.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Weiss-Ishai Sagiv.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Choy Clinton.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Currently in review. 1 cycle(s) to date. Reviewer: Bryan Ong.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Imson Grace.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Planning (CP-ZOC)
SF Planning Department
Approved December 22, 2022. Reviewer: Dacey John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.