Estimated Timeline
Permit issued — plan check completeMarch 28, 2025
Key Milestones
Jul 2021
Permit Filed
New construction permit filed with DBI
Jul 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2023
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Oct 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Mar 2024
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Mar 2025
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 29 mo · Applicant: 0 mo · Dormant: 15 mo
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved March 14, 2025. Reviewer: Long Ian.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved March 06, 2025. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Approved February 25, 2025. Reviewer: Estrella Jerry.
Building Code (BLDG)
Dept. of Building Inspection
Approved February 19, 2025. Reviewer: Mcelroy Carey.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved February 11, 2025. Reviewer: Casey Ryan.
Planning (CP-ZOC)
SF Planning Department
Approved October 12, 2023. Reviewer: Agnihotri Kalyani.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved March 06, 2025. Reviewer: Blackshear John.
Construction
Foundation / Pour
25% completeLatest inspection: Feb 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-25
122REINFORCING STEEL
2026-08-21
122REINFORCING STEELPASSED
2026-08-21
122REINFORCING STEEL
2026-08-19
122REINFORCING STEELPASSED
2026-08-17
122REINFORCING STEELPASSED
2026-08-14
122REINFORCING STEELPASSED
2026-08-11
122REINFORCING STEELPASSED
2026-08-11
122REINFORCING STEEL