Estimated Timeline
0 of 5 stations approved0% complete
Key Milestones
Jul 2021
Permit Filed
New construction permit filed with DBI
Jul 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2021
Currently Dormant
No plan-check activity for 1834 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 1 mo · Applicant: 0 mo · Dormant: 60 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Tam Richard.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Tam Richard.
Mechanical (MECH)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Lai Jeff.
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Tabora Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Brown Richard.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.