Estimated Timeline
5 of 7 stations approved71% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Estrella Jerry.
Planning (CP-ZOC)
SF Planning Department
Approved October 10, 2024. Reviewer: Liang Xinyu.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved October 17, 2024. Reviewer: Imson Grace.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved October 16, 2024. Reviewer: Dennis Rassendyll.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved June 08, 2023. Reviewer: Stacy Sara.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved October 18, 2024. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Nov 2021
Permit Filed
New construction permit filed with DBI
Nov 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.