Estimated Timeline
5 of 7 stations approved71% complete
Key Milestones
Nov 2021
Permit Filed
New construction permit filed with DBI
Nov 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2022
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Aug 2023
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
Oct 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Oct 2024
Currently Dormant
No plan-check activity for 668 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 16 mo · Applicant: 0 mo · Dormant: 42 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Zee Howard.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Estrella Jerry.
Planning (CP-ZOC)
SF Planning Department
Approved October 10, 2024. Reviewer: Liang Xinyu.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved October 17, 2024. Reviewer: Imson Grace.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved October 16, 2024. Reviewer: Dennis Rassendyll.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved June 08, 2023. Reviewer: Stacy Sara.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved October 18, 2024. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.