Estimated Timeline
0 of 6 stations approved0% complete
Key Milestones
Dec 2021
Permit Filed
New construction permit filed with DBI
Dec 2021
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2022
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
Mar 2024
Dormant Period
No plan-check activity for ~16 months — applicant-side pause, not city queue time.
Aug 2025
Currently Dormant
No plan-check activity for 381 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 19 mo · Applicant: 0 mo · Dormant: 37 mo
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on August 11, 2025. 1 round(s) of review. Reviewer: Kwong John.
Public Health (HEALTH)
Dept. of Public Health
Comments issued on March 28, 2024. 1 round(s) of review. Reviewer: Casey Ryan.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on October 19, 2023. 2 round(s) of review. Reviewer: Imson Grace.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Liang Karen.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Estrella Jerry.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Bottleneck Watch: Sidewalk & Street
Sidewalk & Street currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.