San Francisco / Mission / 2530 18Th St

2530 18Th St

73-unit 8-story residential project priortiy processing: erect new 8-story sprinklered type i-b, 73 unit 100% affordaable housing with community rm, common laundry, management offices, hpp prog...

Approved — Awaiting Issuance73 UnitsAB 2011 Ministerial$45.1M Est. Cost
Permit Filed
Jan 2022
Active Review Since
Jan 2022
Review Stations
2 of 9
stations approved
Project Status
Approved
Estimated Timeline

Permit Issuance Estimate

November 2026 — May 2027

Timeline driven by 1 station with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 7 unapproved stations
2 of 9 stations approved22% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on July 12, 2023. 1 round(s) of review. Reviewer: Lau (Nelson) Chi Chiu.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date. Reviewer: Giacomucci Monica.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Chen Bill.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 4 cycle(s) to date. Reviewer: Woo Jason.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Fong Jeffrey.
In Review
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 2 cycle(s) to date. Reviewer: Lee Mira.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved August 01, 2023. Reviewer: Dennis Rassendyll.
Approved
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved July 28, 2023. Reviewer: Chen Bill.
Approved

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Key Milestones
Jan 2022
Permit Filed
New construction permit filed with DBI
Jan 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Data sources: Data from DataSF Building Permits and Building Permit Addenda with Routing datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.