Estimated Timeline
3 of 9 stations approved33% complete
Key Milestones
Feb 2022
Permit Filed
New construction permit filed with DBI
Feb 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2022
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
May 2023
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
May 2024
Currently Dormant
No plan-check activity for 820 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 9 mo · Applicant: 0 mo · Dormant: 46 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on May 10, 2024. 2 round(s) of review. Reviewer: Huang Vivian.
Planning (CP-ZOC)
SF Planning Department
Comments issued on May 28, 2024. 4 round(s) of review. Reviewer: Sacchi Joseph.
Mechanical (MECH)
Dept. of Building Inspection
Comments issued on May 14, 2024. 2 round(s) of review. Reviewer: Tan (Peter) Jia Jian.
Fire (SFFD)
SF Fire Department
Comments issued on May 16, 2024. 2 round(s) of review. Reviewer: Woo Jason.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Ralls Matthew.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved May 29, 2024. Reviewer: Stacy Sara.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved May 15, 2024. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved May 13, 2024. Reviewer: Imson Grace.
Bottleneck Watch: Building Code
Building Code currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.