San Francisco / North Beach / 65 Fresno St

65 Fresno St

5-unit residential project addition of one adu unit at the ground floor of a proposed 4-story, 4-unit residential building under the state adu program.

Dormant5 UnitsAB 2011 MinisterialDBI Valuation $8K
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 9 mo · Applicant: 0 mo
Permit Filed
Feb 2022
Time in Active Review
9 months
excludes 18 months dormant
Review Stations
3 of 9
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 6 unapproved stations
3 of 9 stations approved33% complete
Key Milestones
Feb 2022
Permit Filed
New construction permit filed with DBI
Feb 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2022
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
May 2023
Dormant Period
No plan-check activity for ~11 months — applicant-side pause, not city queue time.
May 2024
Currently Dormant
No plan-check activity for 820 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 9 mo · Applicant: 0 mo · Dormant: 46 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on May 10, 2024. 2 round(s) of review. Reviewer: Huang Vivian.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Comments issued on May 28, 2024. 4 round(s) of review. Reviewer: Sacchi Joseph.
Comments Issued
Mechanical (MECH)
Dept. of Building Inspection
Comments issued on May 14, 2024. 2 round(s) of review. Reviewer: Tan (Peter) Jia Jian.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on May 16, 2024. 2 round(s) of review. Reviewer: Woo Jason.
Comments Issued
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date.
In Review
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Ralls Matthew.
In Review
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved May 29, 2024. Reviewer: Stacy Sara.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved May 15, 2024. Reviewer: Choy Clinton.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved May 13, 2024. Reviewer: Imson Grace.
Approved

Bottleneck Watch: Building Code

Building Code currently has open comments after 2 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.