Estimated Timeline
4 of 8 stations approved50% complete
Key Milestones
Apr 2022
Permit Filed
New construction permit filed with DBI
Apr 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2022
Dormant Period
No plan-check activity for ~7 months — applicant-side pause, not city queue time.
Dec 2024
Currently Dormant
No plan-check activity for 619 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 25 mo · Applicant: 0 mo · Dormant: 28 mo
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on December 04, 2024. 4 round(s) of review. Reviewer: Dennis Rassendyll.
Mechanical (MECH)
Dept. of Building Inspection
Comments issued on December 16, 2024. 3 round(s) of review. Reviewer: Lai Jeff.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 5 cycle(s) to date. Reviewer: Liang Xinyu.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Approved December 16, 2024. Reviewer: Estrella Jerry.
Building Code (BLDG)
Dept. of Building Inspection
Approved December 09, 2024. Reviewer: Huang Vivian.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 27, 2023. Reviewer: Imson Grace.
Mechanical-Electrical (MECH-E)
Dept. of Building Inspection
Approved October 02, 2023. Reviewer: Jacobo Marco.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.