San Francisco / Sunset/Parkside / 2550 Irving St

2550 Irving St

90-unit 7-story residential project to erect 7-story, type i-b, 90 dwelling units bldg with zero basements

Complete90 UnitsAB 2011 MinisterialDBI Valuation $50.0M
Entitlement
Plan Check
Jun 2023
Awaiting Issuance
Jun 2023
Post-Issuance Addenda
Construction
Feb 2026
Complete
Feb 2026
Permit Filed
May 2022
Time in Active Review
14 months
Completed
Feb 2026
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

February 2026

Construction complete — 90 units delivered.

Completion certified by DBI
Permit issued — plan check completeJune 26, 2023
The Story So Far

The 90-unit affordable housing project at 2550 Irving St replaces the former San Francisco Police Credit Union and parking lot with a 7-story building in Sunset/Parkside.

Opposition emerged before the permit filing. In December 2021, the Mid-Sunset Neighborhood Association sued to halt the project, alleging inadequate outreach and objecting to its height and scale, according to the San Francisco Standard. The project filed permit 202205053630 in May 2022 under the AB 2011 ministerial pathway.

The permit record reached a key milestone in June 2023, when the city issued the building permit and completed its review. Further disputes followed. On August 16, 2023, the Board of Appeals rejected an appeal focused on tetrachloroethylene contamination. Mission Local reported that state experts reviewed roughly 5,000 new measurements and found no PCE source within the former dry-cleaning footprint.

On May 10, 2024, San Francisco authorized a $9.6 million property acquisition, a 75-year ground lease, and a development loan of up to $16,956,650. TNDC’s June 2024 groundbreaking plan reserved 22 apartments for families exiting homelessness and 15 for formerly homeless veterans. All homes would serve households earning 25% to 75% of area median income.

Construction began on June 26, 2024, after the neighborhood association failed to secure an injunction and lost permit and demolition appeals, the Chronicle reported. City housing officials estimated that litigation, appeals, consulting, and environmental testing added approximately $1 million to the project’s $99.4 million cost. A neighboring homeowner later disputed construction-related removal of a boundary fence and trees.

The project reached completion in February 2026. In August 2026, a TNDC employee reported that the building was fully occupied, about six weeks ahead of schedule.

Sources: LinkedIn (2026-08) · San Francisco Chronicle (2024-06) · Mission Local (2023-08) · The San Francisco Standard (2021-12) · City and County of San Francisco (2024-05) · Tenderloin Neighborhood Development Corporation (2024-06) · The San Francisco Standard (2024-09)
Updates
Construction complete2026-02-06
Construction complete at 2550 Irving St
Construction finished in February 2026 at 2550 Irving St. The 7-story Sunset/Parkside project adds 90 units under the AB 2011 ministerial pathway.
Key Milestones
May 2022
Permit Filed
New construction permit filed with DBI
May 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2023
Permit Issued
Construction can begin
Feb 2026
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 14 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 5 cycle(s) to date. Reviewer: Laush Maggie.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 4 cycle(s) to date. Reviewer: Casey Ryan.
In Review
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 2 cycle(s) to date. Reviewer: Finnegan John.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 4 cycle(s) to date. Reviewer: Fong Jeffrey.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Wong Irene.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Certified for Occupancy
100% completeLatest inspection: Feb 2026
Construction startedJul 2024
Total inspections92
90 of 90 units certified for occupancy (Initial TCO, Feb 2026).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-05-29
142PRE-FINALPASSED
2026-04-13
148OTHER
2026-03-31
145TCO ISSUED
2026-03-26
142PRE-FINALPASSED
2026-02-10
146MECHANICALPASSED
2026-02-06
145TCO ISSUEDPASSED
2026-01-28
124CEILING INSPECTION
2026-01-27
146MECHANICALPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.