Estimated Timeline
5 of 9 stations approved55% complete
Plan Check Status
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Comments issued on November 03, 2023. 1 round(s) of review. Reviewer: Choy Clinton.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Comments issued on August 16, 2024. 1 round(s) of review. Reviewer: Chan Philip.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Comments issued on November 16, 2023. 1 round(s) of review. Reviewer: Stacy Sara.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved February 04, 2026. Reviewer: Chung Diana.
Fire (SFFD)
SF Fire Department
Approved November 04, 2025. Reviewer: Marsh James.
Planning (CP-ZOC)
SF Planning Department
Approved April 24, 2024. Reviewer: Pantoja Gabriela.
Building Code (BLDG)
Dept. of Building Inspection
Approved July 01, 2025. Reviewer: Ospital Joseph.
Water & Sewer QC (SFPUC-QC)
SF Public Utilities Commission
Approved January 29, 2026. Reviewer: Hoe Cynthia.
Bottleneck Watch: Sidewalk & Street
Sidewalk & Street currently has open comments after 1 round(s) of review. This is the longest-running unapproved station and is the most likely gating item for the next permit issuance window.
Key Milestones
May 2022
Permit Filed
New construction permit filed with DBI
May 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.