Estimated Timeline
4 of 7 stations approved57% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Casey Ryan.
Fire (SFFD)
SF Fire Department
Currently in review. 3 cycle(s) to date. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved August 13, 2025. Reviewer: Kwong John.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved March 15, 2024. Reviewer: Garcia Jobel.
Building Code (BLDG)
Dept. of Building Inspection
Approved April 17, 2023. Reviewer: Mcelroy Carey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved May 15, 2024. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
May 2022
Permit Filed
New construction permit filed with DBI
May 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2026 – May 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.