Estimated Timeline
2 of 7 stations approved28% complete
Key Milestones
May 2022
Permit Filed
New construction permit filed with DBI
May 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Jul 2023
Dormant Period
No plan-check activity for ~8 months — applicant-side pause, not city queue time.
May 2024
Dormant Period
No plan-check activity for ~15 months — applicant-side pause, not city queue time.
Aug 2025
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 19 mo · Applicant: 0 mo · Dormant: 32 mo
Building Code (BLDG)
Dept. of Building Inspection
Cycling through 5 rounds of comments without clearing. Most recent review: August 07, 2026. Reviewer: Mcelroy Carey.
Public Health (HEALTH)
Dept. of Public Health
Comments issued on August 04, 2026. 2 round(s) of review. Reviewer: Casey Ryan.
Fire (SFFD)
SF Fire Department
Comments issued on July 29, 2026. 4 round(s) of review. Reviewer: Andrawes Kamal.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on July 30, 2026. 2 round(s) of review. Reviewer: Garcia Jobel.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 3 cycle(s) to date.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved August 13, 2025. Reviewer: Chan Desmond.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved May 15, 2024. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.