Estimated Timeline
0 of 8 stations approved0% complete
Plan Check Status
Historic Preservation (HIS)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Luton Matt.
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Planning (CP-ZOC)
SF Planning Department
Not yet routed to this station.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Public Health (HEALTH)
Dept. of Public Health
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Bottleneck Watch: Planning
Planning has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.
Key Milestones
Jun 2022
Permit Filed
New construction permit filed with DBI
Jun 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2026 – Jul 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.