San Francisco / Mission / 10 South Van Ness Av

10 South Van Ness Av

966-unit 55-story residential project erect 55-stories over 2-basement, mixed use residential building with 966 dwelling units, retail and services use, and parking

In Plan Check966 UnitsAB 2011 MinisterialDBI Valuation $430.0M
Entitlement
Oct 2022
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: 15 months in active review. City desk: 15 mo · Applicant: 0 mo
Permit Filed
Jun 2022
Time in Active Review
15 months
excludes 35 months dormant
Review Stations
3 of 9
stations approved
Project Status
In Plan Check
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

Timeline driven by 4 stations with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 6 unapproved stations
3 of 9 stations approved33% complete
The Story So Far

The city entitled a 55-story, 966-unit tower at 10 South Van Ness Av in October 2022. The approved mix includes 347 studios, 433 one-bedroom homes, 165 two-bedroom homes and 21 three-bedroom homes. The dossier identifies the project as an AB 2011 ministerial application and lists 0 affordable units.

Permit 202206176565 remains in review as of the August 2026 dossier update. Jim Abrams of J. Abrams Law, P.C. represents the applicant, and Lorabelle Cook is the assigned planner. The record shows 2 dormancy periods, while the permit remains unissued and the project remains incomplete.

The site has long presented development challenges. The San Francisco Business Times reported in March 2015 that a BART tunnel beneath part of the parcel could increase construction costs. In December 2018, Bisnow reported that preservation advocates opposed demolishing the 1927 building associated with Fillmore West, while the developer said incorporating the venue was not viable.

The Chronicle reported that the Planning Commission granted a four-year entitlement extension in January 2023 after Abrams said a prospective lender required it before closing a loan. The publication also reported that Crescent Heights had spent approximately $40 million acquiring 1979 Mission Street and transferring it to the city for low-income housing tied to the project’s affordable-housing obligation.

The proposal later changed. On December 17, 2025, Planning approved a revised 67-story, 820-foot plan with 1,019 homes, including 89 affordable rentals and 656 condominiums, according to the Chronicle. Crescent Heights aimed to begin construction as early as 2027.

As of May 2026, the existing two-story building remained. SFYIMBY reported that NPU Inc. sought permission to hold four to six events per month through mid-May 2029. The latest dossier update still provides no building permit issuance or construction milestone.

Sources: San Francisco Chronicle (2025-12) · San Francisco YIMBY (2026-05) · San Francisco Chronicle (2023-01) · Bisnow (2018-12) · San Francisco Business Times (2015-03) · San Francisco Planning Department (2018-10)
Key Milestones
Jun 2022
Permit Filed
New construction permit filed with DBI
Jun 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Mar 2023
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Mar 2024
Dormant Period
No plan-check activity for ~26 months — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 15 mo · Applicant: 0 mo · Dormant: 35 mo
Building Code (BLDG)
Dept. of Building Inspection
Comments issued on August 17, 2026. 4 round(s) of review. Reviewer: Szeto David.
Comments Issued
Fire (SFFD)
SF Fire Department
Comments issued on July 13, 2026. 2 round(s) of review. Reviewer: Lo Jonathan.
Comments Issued
Water & Sewer (SFPUC)
SF Public Utilities Commission
Comments issued on July 30, 2026. 2 round(s) of review. Reviewer: Garcia Jobel.
Comments Issued
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Comments issued on August 17, 2026. 3 round(s) of review. Reviewer: Zee Howard.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Giacomucci Monica.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved June 08, 2026. Reviewer: Dennis Rassendyll.
Approved
Public Health (HEALTH)
Dept. of Public Health
Approved May 29, 2026. Reviewer: Hoang Tina.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved June 22, 2026. Reviewer: Bryan Ong.
Approved

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.