Estimated Timeline
Permit issued — plan check completeMarch 12, 2025
Key Milestones
Jul 2022
Permit Filed
New construction permit filed with DBI
Jul 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2022
Dormant Period
No plan-check activity for ~18 months — applicant-side pause, not city queue time.
Jun 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Mar 2025
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 1 mo · Dormant: 18 mo
Planning (CP-ZOC)
SF Planning Department
Approved June 27, 2024. Reviewer: Horn Jeffrey.
Building Code (BLDG)
Dept. of Building Inspection
Approved November 19, 2024. Reviewer: Soenksen Richard.
Fire (SFFD)
SF Fire Department
Approved November 06, 2024. Reviewer: Carreira Bela.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved November 01, 2024. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved August 26, 2024. Reviewer: Imson Grace.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved January 29, 2025. Reviewer: Blackshear John.
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.