Estimated Timeline
Permit issued — plan check completeJanuary 08, 2025
Key Milestones
Jul 2022
Permit Filed
New construction permit filed with DBI
Jul 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2023
Dormant Period
No plan-check activity for ~23 months — applicant-side pause, not city queue time.
Jan 2025
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 7 mo · Applicant: 0 mo · Dormant: 23 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Horn Jeffrey.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Bendezu Sebastian.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Kwong John.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 3 cycle(s) to date. Reviewer: Casey Ryan.
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 2 cycle(s) to date. Reviewer: Lee Mira.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Imson Grace.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Foundation / Pour
25% completeLatest inspection: Aug 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-18
123OK TO POURPASSED
2026-08-12
123OK TO POURPASSED
2026-08-03
123OK TO POURPASSED
2026-07-14
122REINFORCING STEELPASSED
2026-07-07
122REINFORCING STEELPASSED
2026-07-02
122REINFORCING STEELPASSED
2026-06-24
123OK TO POURPASSED
2026-06-11
122REINFORCING STEEL