San Francisco / Financial District/South Beach / 200 Folsom St

200 Folsom St

151-unit 9-story residential project erect a 9-story over zero basement type ib, 100% affordable residential building with 151 senior housing units

Complete151 UnitsAB 2011 MinisterialDBI Valuation $57.0M
Entitlement
Plan Check
Oct 2023
Awaiting Issuance
Oct 2023
Post-Issuance Addenda
Construction
Nov 2025
Complete
Nov 2025
Permit Filed
Aug 2022
Time in Active Review
15 months
Completed
Nov 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

October 2023

Permit issued on October 24, 2023. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeOctober 24, 2023
Key Milestones
Aug 2022
Permit Filed
New construction permit filed with DBI
Aug 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2023
Permit Issued
Construction can begin
Nov 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jul 2026
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 15 mo · Applicant: 0 mo
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved October 03, 2023. Reviewer: Garcia Jobel.
Approved
Public Health (HEALTH)
Dept. of Public Health
Approved October 02, 2023. Reviewer: Casey Ryan.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 27, 2023. Reviewer: Dennis Rassendyll.
Approved
Fire (SFFD)
SF Fire Department
Approved September 20, 2023. Reviewer: Andrawes Kamal.
Approved
Disability Access (MOD)
Mayor's Office on Disability
Approved August 22, 2023. Reviewer: Ospital Joseph.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved August 03, 2023. Reviewer: Lau (Nelson) Chi Chiu.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved August 03, 2023. Reviewer: Luu Sarah.
Approved
Construction
Construction Complete
100% completeLatest inspection: May 2026
Construction startedJun 2024
Total inspections97
151 of 151 units certified for occupancy (Initial TCO, Nov 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-07-17
106FINAL INSPECT/APPRVDPASSED
2026-07-17
106FINAL INSPECT/APPRVD
2026-05-18
145TCO ISSUEDPASSED
2026-02-12
111SITE VERIFICATIONPASSED
2025-11-26
145TCO ISSUED
2025-11-25
145TCO ISSUEDPASSED
2025-11-20
145TCO ISSUED
2025-11-07
142PRE-FINAL
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.