Estimated Timeline
Permit issued — plan check completeOctober 24, 2023
Key Milestones
Aug 2022
Permit Filed
New construction permit filed with DBI
Aug 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Oct 2023
Permit Issued
Construction can begin
Nov 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Jul 2026
Construction Complete
Certificate of occupancy issued
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 15 mo · Applicant: 0 mo
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved October 03, 2023. Reviewer: Garcia Jobel.
Public Health (HEALTH)
Dept. of Public Health
Approved October 02, 2023. Reviewer: Casey Ryan.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 27, 2023. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Approved September 20, 2023. Reviewer: Andrawes Kamal.
Disability Access (MOD)
Mayor's Office on Disability
Approved August 22, 2023. Reviewer: Ospital Joseph.
Building Code (BLDG)
Dept. of Building Inspection
Approved August 03, 2023. Reviewer: Lau (Nelson) Chi Chiu.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved August 03, 2023. Reviewer: Luu Sarah.
Construction
Construction Complete
100% completeLatest inspection: May 2026
151 of 151 units certified for occupancy (Initial TCO, Nov 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-07-17
106FINAL INSPECT/APPRVDPASSED
2026-07-17
106FINAL INSPECT/APPRVD
2026-05-18
145TCO ISSUEDPASSED
2026-02-12
111SITE VERIFICATIONPASSED
2025-11-26
145TCO ISSUED
2025-11-25
145TCO ISSUEDPASSED
2025-11-20
145TCO ISSUED
2025-11-07
142PRE-FINAL