Estimated Timeline
1 of 8 stations approved12% complete
Key Milestones
Aug 2022
Permit Filed
New construction permit filed with DBI
Aug 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2023
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Nov 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Nov 2023
Currently Dormant
No plan-check activity for 1029 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 9 mo · Applicant: 0 mo · Dormant: 40 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Kung Melanie.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 1 cycle(s) to date. Reviewer: Dennis Rassendyll.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 2 cycle(s) to date. Reviewer: Der Kristine.
Disability Access (MOD)
Mayor's Office on Disability
Currently in review. 1 cycle(s) to date. Reviewer: Ospital Joseph.
Fire (SFFD)
SF Fire Department
Currently in review. 1 cycle(s) to date. Reviewer: Andrawes Kamal.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 1 cycle(s) to date. Reviewer: Fong Jeffrey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Planning (CP-ZOC)
SF Planning Department
Approved November 02, 2023. Reviewer: Dito Matthew.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.