San Francisco / Hayes Valley / 626 Octavia St

626 Octavia St

40-unit 8-story residential project erect a type 1-a, 8-story over one basement mixed use building with 40 residential unit, retail and parking spaces.

Permit Issued40 UnitsAB 2011 MinisterialDBI Valuation $13.5M
Entitlement
Apr 2022
Plan Check
Aug 2026
Awaiting Issuance
Aug 2026
Post-Issuance Addenda
Construction
Complete
Post-Issuance Addenda: 1 addendum filed — 1 in review.
Permit Filed
Sep 2022
Time in Active Review
16 months
excludes 31 months dormant
Permit Issued
Aug 2026
plan check complete
Project Status
Permit Issued
Estimated Timeline

Permit Issued

August 2026

Permit issued on August 19, 2026. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeAugust 19, 2026
The Story So Far

The proposal at 626 Octavia St began taking shape in 2019, when SocketSite reported a preliminary concept for 30 homes, 15 parking spaces and 7 stories. By 2020, the design had grown to 38 condominiums, including 8 below-market-rate homes, with 25 parking spaces.

The project later expanded to 40 homes across 8 stories. The current mix includes 12 one-bedroom, 26 two-bedroom and 2 three-bedroom homes, with 10 affordable units. March Capital Management, represented by Eduardo Sagues, is pursuing the development through the AB 2011 ministerial pathway.

The Planning Commission approved the project 4-3 on April 28, 2022, according to Streetsblog San Francisco. The approval included a concession for 30 parking spaces instead of the 20 allowed by right. SocketSite reported that the developer viewed the additional parking as important to financial viability amid high construction costs and market volatility.

The project secured entitlements in April 2022, and the applicant filed building permit 202209273243 in September 2022. Plans reported by San Francisco YIMBY included two retail spaces, parking for 30 cars and 46 bicycles, and four permanently subsidized replacement homes for residents of the existing building.

Progress later stalled. HVSafe reported on April 15, 2025, that March Capital had placed construction plans on hold because of challenging business and market conditions. LoopNet listed the fully entitled, site-permit-ready property for sale on April 17, 2025, but no longer advertises it. As of April 2025, the site still held a four-unit residential building and a parking lot with more than 20 spaces.

The latest dossier update records the building permit as issued in August 2026 after 2 dormancy periods. The permit issuance clears a key administrative step, but the record does not establish whether construction has started.

Sources: HVSafe (2025-04) · LoopNet (2025-04) · Streetsblog San Francisco (2022-04) · SocketSite (2022-04) · San Francisco YIMBY (2022-10) · HVSafe (2022-04) · SocketSite (2020-05) · SocketSite (2019-03)
Key Milestones
Sep 2022
Permit Filed
New construction permit filed with DBI
Sep 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2023
Dormant Period
No plan-check activity for ~10 months — applicant-side pause, not city queue time.
Jun 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jul 2024
Dormant Period
No plan-check activity for ~21 months — applicant-side pause, not city queue time.
Aug 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 16 mo · Applicant: 0 mo · Dormant: 31 mo
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 1 cycle(s) to date. Reviewer: Barnes Jeff.
In Review
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Chen Bill.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Lo Jonathan.
In Review
Planning (CP-ZOC)
SF Planning Department
Approved June 28, 2024. Reviewer: Enchill Charles.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved July 19, 2024. Reviewer: Imson Grace.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved August 16, 2023. Reviewer: Dennis Rassendyll.
Approved
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved July 20, 2023. Reviewer: Chen Bill.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved July 02, 2024. Reviewer: Blackshear John.
Approved

Bottleneck Watch: Building Code

Building Code is the longest-running active review station on this project.

Post-Issuance Addenda
Addendum #1In Review
0 of 2 stations approved· last activity 2026-08
Construction
Permit issued — no DBI inspection records yet.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.