Estimated Timeline
Permit issued — plan check completeMay 13, 2024
Key Milestones
Sep 2022
Permit Filed
New construction permit filed with DBI
Sep 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
May 2024
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 19 mo · Applicant: 0 mo
Building Code (BLDG)
Dept. of Building Inspection
Approved April 30, 2024. Reviewer: Barnes Jeff.
Fire (SFFD)
SF Fire Department
Approved April 29, 2024. Reviewer: Woo Jason.
Planning (CP-ZOC)
SF Planning Department
Approved November 01, 2023. Reviewer: Feeney Claire.
Public Health (HEALTH)
Dept. of Public Health
Approved November 09, 2023. Reviewer: Chen Bill.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved November 06, 2023. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 19, 2023. Reviewer: Imson Grace.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved August 01, 2023. Reviewer: Bryan Ong.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved November 06, 2023. Reviewer: Blackshear John.
Construction
Drywall / Sheetrock
75% completeLatest inspection: Mar 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-13
125ROUGH FRAME, PARTIALPASSED
2026-07-30
125ROUGH FRAME, PARTIALPASSED
2026-07-21
125ROUGH FRAME, PARTIALPASSED
2026-07-16
125ROUGH FRAME, PARTIALPASSED
2026-07-02
125ROUGH FRAME, PARTIALPASSED
2026-06-30
125ROUGH FRAME, PARTIALPASSED
2026-06-25
125ROUGH FRAME, PARTIALPASSED
2026-06-23
125ROUGH FRAME, PARTIALPASSED