Estimated Timeline
8 of 10 stations approved80% complete
Plan Check Status
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Cheng Rachel.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
Planning (CP-ZOC)
SF Planning Department
Approved September 20, 2023. Reviewer: Horn Jeffrey.
Building Code (BLDG)
Dept. of Building Inspection
Approved September 26, 2023. Reviewer: Ospital Joseph.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 15, 2023. Reviewer: Dennis Rassendyll.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 13, 2023. Reviewer: Garcia Jobel.
Fire (SFFD)
SF Fire Department
Approved August 15, 2023. Reviewer: Woo Jason.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved August 10, 2023. Reviewer: Casey Ryan.
Disability Access (MOD)
Mayor's Office on Disability
Approved August 09, 2023. Reviewer: Ospital Joseph.
Hazmat (HEALTH-HM)
Dept. of Public Health
Approved August 07, 2023. Reviewer: Yim Raymond.
Bottleneck Watch: Public Health
Public Health is the longest-running active review station on this project.
Key Milestones
Nov 2022
Permit Filed
New construction permit filed with DBI
Nov 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Oct 2023
Permit Issued
Construction can begin