San Francisco / Mission / 1939 Market St

1939 Market St

187-unit 15-story residential project erect a 15 story bldg with 187 dwelling units, residential/commercial(warmshell) ,type 1a

Permit Issued — Under Construction187 UnitsAB 2011 Ministerial$86.7M Est. Cost
Permit Filed
Nov 2022
Active Review Since
Nov 2022
Review Stations
8 of 10
stations approved
Project Status
Issued
Estimated Timeline

Permit Issued

October 2023

Permit issued on October 13, 2023. Project moved into construction phase.

Actual permit issuance date from DBI records
8 of 10 stations approved80% complete
Plan Check Status
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Cheng Rachel.
In Review
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Currently in review. 1 cycle(s) to date. Reviewer: Blackshear John.
In Review
Planning (CP-ZOC)
SF Planning Department
Approved September 20, 2023. Reviewer: Horn Jeffrey.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved September 26, 2023. Reviewer: Ospital Joseph.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 15, 2023. Reviewer: Dennis Rassendyll.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 13, 2023. Reviewer: Garcia Jobel.
Approved
Fire (SFFD)
SF Fire Department
Approved August 15, 2023. Reviewer: Woo Jason.
Approved
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved August 10, 2023. Reviewer: Casey Ryan.
Approved
Disability Access (MOD)
Mayor's Office on Disability
Approved August 09, 2023. Reviewer: Ospital Joseph.
Approved
Hazmat (HEALTH-HM)
Dept. of Public Health
Approved August 07, 2023. Reviewer: Yim Raymond.
Approved

Bottleneck Watch: Public Health

Public Health is the longest-running active review station on this project.

Key Milestones
Nov 2022
Permit Filed
New construction permit filed with DBI
Nov 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Oct 2023
Permit Issued
Construction can begin