Estimated Timeline
Permit issued — plan check completeAugust 12, 2024
Key Milestones
Nov 2022
Permit Filed
New construction permit filed with DBI
Nov 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Feb 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Feb 2024
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Aug 2024
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 15 mo · Applicant: 0 mo · Dormant: 6 mo
Planning (CP-ZOC)
SF Planning Department
Approved February 05, 2024. Reviewer: Durandet Kimberly.
Building Code (BLDG)
Dept. of Building Inspection
Approved February 05, 2024. Reviewer: Mcelroy Carey.
Disability Access (MOD)
Mayor's Office on Disability
Approved February 05, 2024. Reviewer: Lee Mira.
Fire (SFFD)
SF Fire Department
Approved February 05, 2024. Reviewer: Andrawes Kamal.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 31, 2024. Reviewer: Kwong John.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 01, 2023. Reviewer: Fong Jeffrey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved February 08, 2024. Reviewer: Blackshear John.
Construction
Rough Framing
40% completeLatest inspection: Jul 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-26
125ROUGH FRAME, PARTIALPASSED
2026-08-24
125ROUGH FRAME, PARTIALPASSED
2026-08-24
125ROUGH FRAME, PARTIAL
2026-08-21
125ROUGH FRAME, PARTIAL
2026-08-20
125ROUGH FRAME, PARTIALPASSED
2026-08-19
125ROUGH FRAME, PARTIALPASSED
2026-08-18
125ROUGH FRAME, PARTIALPASSED
2026-08-17
125ROUGH FRAME, PARTIALPASSED