Estimated Timeline
9 of 9 stations approved100% complete
Plan Check Status
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved November 14, 2023. Reviewer: Garcia Jobel.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved October 06, 2023. Reviewer: Casey Ryan.
Disability Access (MOD)
Mayor's Office on Disability
Approved October 06, 2023. Reviewer: Ospital Joseph.
Hazmat (HEALTH-HM)
Dept. of Public Health
Approved October 04, 2023. Reviewer: Chan Thomas.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 27, 2023. Reviewer: Kwong John.
Fire (SFFD)
SF Fire Department
Approved September 01, 2023. Reviewer: Berona Marcus.
Public Health (HEALTH)
Dept. of Public Health
Approved August 29, 2023. Reviewer: Flores Antoniette.
Building Code (BLDG)
Dept. of Building Inspection
Approved August 24, 2023. Reviewer: Lau (Nelson) Chi Chiu.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved October 12, 2023. Reviewer: Blackshear John.
Key Milestones
Nov 2022
Permit Filed
New construction permit filed with DBI
Nov 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Nov 2023
Permit Issued
Construction can begin