Estimated Timeline
Permit issued — plan check completeJune 11, 2024
Key Milestones
Nov 2022
Permit Filed
New construction permit filed with DBI
Nov 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Feb 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jun 2024
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 9 mo · Applicant: 0 mo · Dormant: 9 mo
Planning (CP-ZOC)
SF Planning Department
Approved February 27, 2024. Reviewer: Durandet Kimberly.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved February 06, 2024. Reviewer: Chan Desmond.
Building Code (BLDG)
Dept. of Building Inspection
Approved January 11, 2024. Reviewer: Bendezu Sebastian.
Fire (SFFD)
SF Fire Department
Approved December 27, 2023. Reviewer: Andrawes Kamal.
Public Health (HEALTH)
Dept. of Public Health
Approved December 13, 2023. Reviewer: Casey Ryan.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved November 22, 2023. Reviewer: Fong Jeffrey.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved November 06, 2023. Reviewer: Mautner Allegra.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved January 19, 2024. Reviewer: Yin Diane.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved February 14, 2024. Reviewer: Blackshear John.
Construction
Mechanical / MEP
80% completeLatest inspection: Jul 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-26
134OK TO COVERPASSED
2026-08-24
134OK TO COVERPASSED
2026-08-20
134OK TO COVERPASSED
2026-08-18
134OK TO COVERPASSED
2026-08-13
134OK TO COVERPASSED
2026-08-11
134OK TO COVERPASSED
2026-08-06
134OK TO COVERPASSED
2026-08-04
134OK TO COVER