Estimated Timeline
1 of 9 stations approved11% complete
Key Milestones
Nov 2022
Permit Filed
New construction permit filed with DBI
Nov 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Dormant Period
No plan-check activity for ~40 months — applicant-side pause, not city queue time.
Apr 2027 – Oct 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 4 mo · Applicant: 0 mo · Dormant: 40 mo
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Comments issued on April 15, 2026. 1 round(s) of review. Reviewer: Chen Bill.
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Dito Matthew.
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Public Health (HEALTH)
Dept. of Public Health
Approved April 15, 2026. Reviewer: Chen Bill.
Bottleneck Watch: Fire
Fire has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.