San Francisco / Presidio Heights / 91 Wood St

91 Wood St

42-unit 6-story residential project to erect a 6-story, 1-basement, 42 dwelling units, type iii-a over 1-a, mixed-use building.

In Plan Check42 UnitsAB 2011 MinisterialDBI Valuation $14.0M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: 4 months in active review. City desk: 4 mo · Applicant: 0 mo
Permit Filed
Nov 2022
Time in Active Review
4 months
excludes 40 months dormant
Review Stations
1 of 9
stations approved
Project Status
In Plan Check
Estimated Timeline

Permit Issuance Estimate

April 2027 — October 2028

Timeline driven by 1 station with open comments. Optimistic case assumes remaining stations clear at the 25th-percentile pace for comparable projects; pessimistic case uses the 75th-percentile.

V0 empirical baselines from 8 unapproved stations
1 of 9 stations approved11% complete
Key Milestones
Nov 2022
Permit Filed
New construction permit filed with DBI
Nov 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Dormant Period
No plan-check activity for ~40 months — applicant-side pause, not city queue time.
Apr 2027 – Oct 2028
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 4 mo · Applicant: 0 mo · Dormant: 40 mo
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Comments issued on April 15, 2026. 1 round(s) of review. Reviewer: Chen Bill.
Comments Issued
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Dito Matthew.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Not Yet Routed
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Not Yet Routed
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Not Yet Routed
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Not yet routed to this station.
Not Yet Routed
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Not Yet Routed
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Not Yet Routed
Public Health (HEALTH)
Dept. of Public Health
Approved April 15, 2026. Reviewer: Chen Bill.
Approved

Bottleneck Watch: Fire

Fire has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.