Estimated Timeline
7 of 9 stations approved77% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Hicks Bridget.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 28, 2023. Reviewer: Stacy Sara.
Public Health (HEALTH)
Dept. of Public Health
Approved September 25, 2023. Reviewer: Casey Ryan.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 22, 2023. Reviewer: Fong Jeffrey.
Building Code (BLDG)
Dept. of Building Inspection
Approved September 21, 2023. Reviewer: Soenksen Richard.
Fire (SFFD)
SF Fire Department
Approved September 20, 2023. Reviewer: Andrawes Kamal.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved September 25, 2023. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved October 02, 2023. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Key Milestones
Dec 2022
Permit Filed
New construction permit filed with DBI
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2023
Permit Issued
Construction can begin