Estimated Timeline
Permit issued — plan check completeDecember 01, 2023
Key Milestones
Dec 2022
Permit Filed
New construction permit filed with DBI
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2023
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Hicks Bridget.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 28, 2023. Reviewer: Stacy Sara.
Public Health (HEALTH)
Dept. of Public Health
Approved September 25, 2023. Reviewer: Casey Ryan.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 22, 2023. Reviewer: Fong Jeffrey.
Building Code (BLDG)
Dept. of Building Inspection
Approved September 21, 2023. Reviewer: Soenksen Richard.
Fire (SFFD)
SF Fire Department
Approved September 20, 2023. Reviewer: Andrawes Kamal.
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved September 25, 2023. Reviewer: Casey Ryan.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved October 02, 2023. Reviewer: Blackshear John.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.
Construction
Drywall / Sheetrock
75% completeLatest inspection: Aug 2026
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-26
154OK TO COVER, PARTIALPASSED
2026-08-24
135SHEETROCK NAILINGPASSED
2026-08-17
154OK TO COVER, PARTIAL
2026-08-13
154OK TO COVER, PARTIALPASSED
2026-08-06
154OK TO COVER, PARTIALPASSED
2026-07-28
134OK TO COVERPASSED
2026-07-13
126ROUGH FRAMEPASSED
2026-06-26
134OK TO COVERPASSED