San Francisco / Western Addition / 850 Turk St

850 Turk St

92-unit 8-story residential project priority processing - 100% affordable housing

Permit Issued92 UnitsAB 2011 MinisterialDBI Valuation $39.0M
Entitlement
Plan Check
Dec 2023
Awaiting Issuance
Dec 2023
Post-Issuance Addenda
Construction
Complete
Construction: Drywall / Sheetrock (75%). Last inspection: Aug 2026.
Permit Filed
Dec 2022
Time in Active Review
12 months
Permit Issued
Dec 2023
plan check complete
Project Status
Permit Issued
Estimated Timeline

Permit Issued

December 2023

Permit issued on December 01, 2023. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeDecember 01, 2023
Key Milestones
Dec 2022
Permit Filed
New construction permit filed with DBI
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2023
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 12 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 1 cycle(s) to date. Reviewer: Hicks Bridget.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Dennis Rassendyll.
In Review
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved September 28, 2023. Reviewer: Stacy Sara.
Approved
Public Health (HEALTH)
Dept. of Public Health
Approved September 25, 2023. Reviewer: Casey Ryan.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 22, 2023. Reviewer: Fong Jeffrey.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved September 21, 2023. Reviewer: Soenksen Richard.
Approved
Fire (SFFD)
SF Fire Department
Approved September 20, 2023. Reviewer: Andrawes Kamal.
Approved
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved September 25, 2023. Reviewer: Casey Ryan.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved October 02, 2023. Reviewer: Blackshear John.
Approved

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Construction
Drywall / Sheetrock
75% completeLatest inspection: Aug 2026
Construction startedJun 2025
Total inspections33
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-26
154OK TO COVER, PARTIALPASSED
2026-08-24
135SHEETROCK NAILINGPASSED
2026-08-17
154OK TO COVER, PARTIAL
2026-08-13
154OK TO COVER, PARTIALPASSED
2026-08-06
154OK TO COVER, PARTIALPASSED
2026-07-28
134OK TO COVERPASSED
2026-07-13
126ROUGH FRAMEPASSED
2026-06-26
134OK TO COVERPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.