Estimated Timeline
8 of 8 stations approved100% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Approved May 09, 2025. Reviewer: Feeney Claire.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved June 04, 2025. Reviewer: Bryan Ong.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved January 10, 2025. Reviewer: Long Ian.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved January 09, 2025. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Approved January 08, 2025. Reviewer: Estrella Jerry.
Building Code (BLDG)
Dept. of Building Inspection
Approved January 07, 2025. Reviewer: Finnegan John.
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved October 18, 2023. Reviewer: Hom Calvin.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved March 11, 2025. Reviewer: Blackshear John.
Key Milestones
Dec 2022
Permit Filed
New construction permit filed with DBI
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
May 2025
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Apr 2026 – May 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.