Estimated Timeline
10 of 10 stations approved100% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Approved June 04, 2024. Reviewer: Westoff Alex.
Public Health (HEALTH)
Dept. of Public Health
Approved July 05, 2024. Reviewer: Casey Ryan.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved June 06, 2024. Reviewer: Dennis Rassendyll.
Hazmat (HEALTH-HM)
Dept. of Public Health
Approved June 06, 2024. Reviewer: Chan Thomas.
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved June 06, 2024. Reviewer: Casey Ryan.
Fire (SFFD)
SF Fire Department
Approved March 11, 2024. Reviewer: Estrella Jerry.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved February 08, 2024. Reviewer: Dottson Marcus.
Building Code (BLDG)
Dept. of Building Inspection
Approved November 17, 2023. Reviewer: Lau (Nelson) Chi Chiu.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved August 15, 2023. Reviewer: Fong Jeffrey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 10, 2024. Reviewer: Blackshear John.
Key Milestones
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Permit Filed
New construction permit filed with DBI
Jun 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Sep 2024
Permit Issued
Construction can begin