San Francisco / Mission / 80 Julian Av

80 Julian Av

21-unit 6-story residential project priority process per ab-004: to erect a 6-story & 2 basements, type iv-c, mixed used building.

Permit Issued — Under Construction21 UnitsAB 2011 Ministerial$27.0M Est. Cost
Permit Filed
Dec 2022
Active Review Since
Dec 2022
Review Stations
10 of 10
stations approved
Project Status
Issued
Estimated Timeline

Permit Issued

September 2024

Permit issued on September 12, 2024. Project moved into construction phase.

Actual permit issuance date from DBI records
10 of 10 stations approved100% complete
Plan Check Status
Planning (CP-ZOC)
SF Planning Department
Approved June 04, 2024. Reviewer: Westoff Alex.
Approved
Public Health (HEALTH)
Dept. of Public Health
Approved July 05, 2024. Reviewer: Casey Ryan.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved June 06, 2024. Reviewer: Dennis Rassendyll.
Approved
Hazmat (HEALTH-HM)
Dept. of Public Health
Approved June 06, 2024. Reviewer: Chan Thomas.
Approved
Mental Health (HEALTH-MH)
Dept. of Public Health
Approved June 06, 2024. Reviewer: Casey Ryan.
Approved
Fire (SFFD)
SF Fire Department
Approved March 11, 2024. Reviewer: Estrella Jerry.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved February 08, 2024. Reviewer: Dottson Marcus.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved November 17, 2023. Reviewer: Lau (Nelson) Chi Chiu.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved August 15, 2023. Reviewer: Fong Jeffrey.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 10, 2024. Reviewer: Blackshear John.
Approved
Key Milestones
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Permit Filed
New construction permit filed with DBI
Jun 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Sep 2024
Permit Issued
Construction can begin