Estimated Timeline
3 of 8 stations approved37% complete
Plan Check Status
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 3 cycle(s) to date. Reviewer: Bendezu Sebastian.
Public Health (HEALTH)
Dept. of Public Health
Currently in review. 1 cycle(s) to date. Reviewer: Chen Bill.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: Woo Jason.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 3 cycle(s) to date. Reviewer: Fong Jeffrey.
Mental Health (HEALTH-MH)
Dept. of Public Health
Currently in review. 3 cycle(s) to date. Reviewer: Chen Bill.
Planning (CP-ZOC)
SF Planning Department
Approved August 10, 2023. Reviewer: Ajello Laura.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved August 03, 2023. Reviewer: Dennis Rassendyll.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved August 10, 2023. Reviewer: Blackshear John.
Bottleneck Watch: Building Code
Building Code is the longest-running active review station on this project.
Key Milestones
Dec 2022
Permit Filed
New construction permit filed with DBI
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Sep 2023
Permit Issued
Construction can begin
Feb 2026
Construction Complete
Certificate of occupancy issued