Estimated Timeline
Permit issued — plan check completeJuly 07, 2026
Key Milestones
Dec 2022
Permit Filed
New construction permit filed with DBI
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Dormant Period
No plan-check activity for ~9 months — applicant-side pause, not city queue time.
Dec 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Apr 2025
Dormant Period
No plan-check activity for ~15 months — applicant-side pause, not city queue time.
Jul 2026
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 18 mo · Applicant: 0 mo · Dormant: 25 mo
Building Code (BLDG)
Dept. of Building Inspection
Approved August 30, 2024. Reviewer: Lau (Nelson) Chi Chiu.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved July 03, 2024. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Approved June 13, 2024. Reviewer: Ziegler Erik.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved October 03, 2024. Reviewer: Nawbary Susan.
Planning (CP-ZOC)
SF Planning Department
Approved December 15, 2023. Reviewer: Horn Jeffrey.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved December 28, 2023. Reviewer: Fong Jeffrey.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved March 14, 2025. Reviewer: Blackshear John.
Post-Issuance Addenda
Addendum #1In Review
0 of 1 stations approved
Construction
Permit issued — no DBI inspection records yet. Street-use permit active from Oct 2025.
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.