Estimated Timeline
0 of 8 stations approved0% complete
Key Milestones
Dec 2022
Permit Filed
New construction permit filed with DBI
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Dec 2022
Dormant Period
No plan-check activity for ~28 months — applicant-side pause, not city queue time.
May 2025
Dormant Period
No plan-check activity for ~13 months — applicant-side pause, not city queue time.
Mar 2027 – Oct 2029
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 3 mo · Applicant: 0 mo · Dormant: 41 mo
Building Code (BLDG)
Dept. of Building Inspection
Not yet routed to this station.
Planning (CP-ZOC)
SF Planning Department
Not yet routed to this station.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Not yet routed to this station.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Not yet routed to this station.
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Not yet routed to this station.
Public Health (HEALTH)
Dept. of Public Health
Not yet routed to this station.
Fire (SFFD)
SF Fire Department
Not yet routed to this station.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Not yet routed to this station.
Bottleneck Watch: Sidewalk & Street
Sidewalk & Street has not yet been routed for review. Until it begins active review, it remains an unresolved dependency on the critical path.