San Francisco / Potrero Hill / 1212 Maryland St

1212 Maryland St

105-unit 8-story residential project mayor dir 13-01 & 17-02 priority project: erect a 8-story, type 1b, residential/mixed use building, with 105 residential units, retail, assembly, office

Complete105 UnitsAB 2011 MinisterialDBI Valuation $35.0M
Entitlement
Plan Check
Oct 2023
Awaiting Issuance
Oct 2023
Post-Issuance Addenda
Construction
Aug 2025
Complete
Aug 2025
Permit Filed
Dec 2022
Time in Active Review
10 months
Completed
Aug 2025
units certified for occupancy
Project Status
Complete
Estimated Timeline

Permit Issued

August 2025

Construction complete — 105 units delivered.

Completion certified by DBI
Permit issued — plan check completeOctober 25, 2023
Key Milestones
Dec 2022
Permit Filed
New construction permit filed with DBI
Dec 2022
Electronic Plan Review Activated
Plans distributed to all review stations
Sep 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Oct 2023
Permit Issued
Construction can begin
Aug 2025
Units Certified for Occupancy
Temporary Certificate of Occupancy (TCO) issued — residents can move in.
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 10 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Approved September 19, 2023. Reviewer: Giacomucci Monica.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 21, 2023. Reviewer: Dennis Rassendyll.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 15, 2023. Reviewer: Garcia Jobel.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved August 16, 2023. Reviewer: Mautner Allegra.
Approved
Fire (SFFD)
SF Fire Department
Approved August 11, 2023. Reviewer: Berona Marcus.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved August 09, 2023. Reviewer: Mcelroy Carey.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved September 18, 2023. Reviewer: Blackshear John.
Approved
Construction
Certified for Occupancy
100% completeLatest inspection: Feb 2026
Construction startedAug 2024
Total inspections90
105 of 105 units certified for occupancy (Initial TCO, Aug 2025).
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-25
106FINAL INSPECT/APPRVD
2026-02-13
145TCO ISSUEDPASSED
2025-09-17
142PRE-FINAL
2025-09-09
142PRE-FINAL
2025-07-25
148OTHER
2025-07-18
142PRE-FINAL
2025-07-16
142PRE-FINAL
2025-07-14
142PRE-FINAL
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.