Estimated Timeline
8 of 8 stations approved100% complete
Key Milestones
Mar 2023
Permit Filed
New construction permit filed with DBI
Mar 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Aug 2023
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Sep 2023
Dormant Period
No plan-check activity for ~6 months — applicant-side pause, not city queue time.
Jun 2024
Currently Dormant
No plan-check activity for 791 days so far — applicant-side pause, not city queue time.
Sep 2026 – Sep 2026
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 9 mo · Applicant: 0 mo · Dormant: 32 mo
Public Health (HEALTH)
Dept. of Public Health
Approved June 27, 2024. Reviewer: Hoang Tina.
Building Code (BLDG)
Dept. of Building Inspection
Approved September 18, 2023. Reviewer: Soenksen Richard.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved September 18, 2023. Reviewer: Dennis Rassendyll.
Fire (SFFD)
SF Fire Department
Approved September 14, 2023. Reviewer: Andrawes Kamal.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved September 14, 2023. Reviewer: Fong Jeffrey.
Planning (CP-ZOC)
SF Planning Department
Approved August 29, 2023. Reviewer: Ajello Laura.
Disability Access (MOD)
Mayor's Office on Disability
Approved August 23, 2023. Reviewer: Ospital Joseph.
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved September 19, 2023. Reviewer: Blackshear John.