Estimated Timeline
0 of 5 stations approved0% complete
Key Milestones
May 2023
Permit Filed
New construction permit filed with DBI
May 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2023
Currently Dormant
No plan-check activity for 1168 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 2 mo · Applicant: 0 mo · Dormant: 38 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Samonsky Ella.
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: La Eace Robert.
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Szeto David.
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Imson Grace.
Bottleneck Watch: Planning
Planning is the longest-running active review station on this project.