San Francisco / Mission / 1979 Mission St

1979 Mission St

60-unit 1-story residential project prj-023-0529: priority process per ab-004: erect type-v tiny cabins for temporary homeless shelter community.

Dormant60 UnitsStandard EntitlementDBI Valuation $4.4M
Entitlement
Plan Check
Awaiting Issuance
Post-Issuance Addenda
Construction
Complete
Plan Check: Dormant — no activity for 180+ days. City desk: 2 mo · Applicant: 0 mo
Permit Filed
May 2023
Time in Active Review
2 months
Review Stations
0 of 5
stations approved
Project Status
Dormant
Estimated Timeline

Permit Issuance Estimate

March 2027 — September 2027

No active review activity yet — estimate falls back to median durations for comparable SF projects of this size.

V0 empirical baselines from 5 unapproved stations
0 of 5 stations approved0% complete
Key Milestones
May 2023
Permit Filed
New construction permit filed with DBI
May 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Jun 2023
Currently Dormant
No plan-check activity for 1168 days so far — applicant-side pause, not city queue time.
Mar 2027 – Sep 2027
Estimated Permit Issuance
All stations approved, fees collected, permit issued.
Plan Check Status
City desk: 2 mo · Applicant: 0 mo · Dormant: 38 mo
Planning (CP-ZOC)
SF Planning Department
Currently in review. 2 cycle(s) to date. Reviewer: Samonsky Ella.
In Review
Fire (SFFD)
SF Fire Department
Currently in review. 2 cycle(s) to date. Reviewer: La Eace Robert.
In Review
Building Code (BLDG)
Dept. of Building Inspection
Currently in review. 2 cycle(s) to date. Reviewer: Szeto David.
In Review
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Currently in review. 2 cycle(s) to date. Reviewer: Choy Clinton.
In Review
Water & Sewer (SFPUC)
SF Public Utilities Commission
Currently in review. 2 cycle(s) to date. Reviewer: Imson Grace.
In Review

Bottleneck Watch: Planning

Planning is the longest-running active review station on this project.

Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.