San Francisco / Mission / 1515 South Van Ness Av

1515 South Van Ness Av

168-unit 9-story residential project mohcd

Permit Issued168 UnitsAB 2011 MinisterialDBI Valuation $59.6M
Entitlement
Plan Check
Jun 2024
Awaiting Issuance
Jun 2024
Post-Issuance Addenda
Construction
Complete
Construction: Drywall / Sheetrock (75%). Last inspection: May 2026.
Permit Filed
Jun 2023
Time in Active Review
13 months
Permit Issued
Jun 2024
plan check complete
Project Status
Permit Issued
Estimated Timeline

Permit Issued

June 2024

Permit issued on June 20, 2024. Project moved into construction phase.

Actual permit issuance date from DBI records
Permit issued — plan check completeJune 20, 2024
Key Milestones
Jun 2023
Permit Filed
New construction permit filed with DBI
Jun 2023
Electronic Plan Review Activated
Plans distributed to all review stations
Apr 2024
Planning Approved
CP-ZOC signed off — biggest institutional hurdle cleared
Jun 2024
Permit Issued
Construction can begin
Plan Check Status
Station statuses below are historical; the permit has been issued.
City desk: 13 mo · Applicant: 0 mo
Planning (CP-ZOC)
SF Planning Department
Approved April 19, 2024. Reviewer: Pantoja Gabriela.
Approved
Building Code (BLDG)
Dept. of Building Inspection
Approved March 25, 2024. Reviewer: Soenksen Richard.
Approved
Plan Approval Struct. (PAD-STR)
Dept. of Building Inspection
Approved March 18, 2024. Reviewer: Ng Jacky.
Approved
Urban Forestry (DPW-BUF)
DPW — Bureau of Urban Forestry
Approved June 05, 2024. Reviewer: Mautner Allegra.
Approved
Fire (SFFD)
SF Fire Department
Approved March 18, 2024. Reviewer: Andrawes Kamal.
Approved
Water & Sewer (SFPUC)
SF Public Utilities Commission
Approved February 02, 2024. Reviewer: Fong Jeffrey.
Approved
Sidewalk & Street (DPW-BSM)
DPW — Bureau of Street & Mapping
Approved November 16, 2023. Reviewer: Devine Theo.
Approved
Labor Compliance (DFCU)
Office of Econ. & Workforce Dev.
Approved June 05, 2024. Reviewer: Blackshear John.
Approved
Maher Site Mitigation (HEALTH-MH)
Dept. of Public Health
Approved May 23, 2024. Reviewer: Chen Bill.
Approved
Construction
Drywall / Sheetrock
75% completeLatest inspection: May 2026
Construction startedMay 2025
Total inspections40
Trade permits (electrical, plumbing) are tracked separately by DBI and not shown yet.
Recent Inspections
2026-08-21
126ROUGH FRAME
2026-08-05
133LATH, EXTERIOR
2026-07-28
134OK TO COVER
2026-07-27
133LATH, EXTERIORPASSED
2026-07-22
133LATH, EXTERIORPASSED
2026-07-13
126ROUGH FRAME
2026-07-07
135SHEETROCK NAILING
2026-07-06
126ROUGH FRAMEPASSED
Data sources: Data from DataSF Building Permits, Building Permit Addenda with Routing, DPW Street-Use Permits, MOHCD Affordable Housing Pipeline, and Dwelling Unit Completion Counts datasets. Timeline estimates are statistical projections, not guarantees. See DataSF Building Permit Addenda with Routing.